Detailed commissioning steps
21
87 |
Building Technologies
21.18 Testing detectors
The commissioning personnel perform the function test for the ↑ automatic fire
detectors and the 'Manual call points'.
information about the individual steps on the specified
pages.
ϖ The ↑ detector line has been commissioned.
1. Switch the test mode on. Link [➙ 89]
2. Initiate the detector. Link [➙ 87]
3. Switch normal operation on. Link [➙ 90]
4. Test the logged test activations. Link [➙ 87]
21.18.1 Activate the detector
ϖ DETECTOR TEST is switched on.
1. Activate all automatic 'Detectors' and 'Manual call points' using the
corresponding tools.
2. Write down the sequence of the test activations.
The ↑ alarm indicator for the activated detector flashes at each test activation.
If an ↑ external alarm indicator is connected and correspondingly configured,
the external alarm indicator also lights up.
You will find information about triggering detectors in document 007004. See
chapter 'Applicable documents'.
See also
1 Applicable documents [➙ 11]
21.18.2 Testing logged test activations
1. Test the logged test activations. This can be done in two ways:
– ↑ Person Machine Interface: Select 'Event memory' in the main menu.
– SintesoWorks: Select the 'Commissioning' > 'Upload site event memory'
menu items.
2. Rectify existing errors if necessary, e.g., if the ↑ alarm indicator has not flashed
or no test entries exist.