Detaile
d commissioning steps
Switch on normal operation
21
90 | 188
Building Technologies
009052_s_en_
--
Fire Safety
2016
-
-
02
21.21 Switch on normal operation
There is a shortened procedure for switching individual '
Zones
' to
normal
operation. The procedure is described in the following section: 'Switching 'Zone' to
normal operation'
Switching 'Area', 'Section' or 'Zone' to normal operation
1. Select 'Topology' > 'Detection tree' in the main menu.
2. Select the element you want to switch to normal operation: 'Area', 'Section' or
'Zone'
3. Press the 'More Options' softkey and select 'Execute commands'.
4. Select a command from the following table.
The element is switched to normal operation.
The yellow 'DETECTOR TEST' LED goes out.
Element Command
Area 'Non-MCP zones det.test END'
'MCP zones det.test END'
Section 'Non-MCP zones det.test END'
'MCP zones det.test END'
Zone 'Detector test END'
Commands under 'Execute commands'
You can also switch to
normal operation at superordinate level for the
command in question. Test mode can also be exited in the 'Zone', 'Section' or
'Area', for example.
Switching 'Zone' to normal operation
There is a shortened procedure for switching individual 'Zones' to normal operation:
1. Select 'Message summary' > 'Test message' in the main menu.
2. Select the displayed 'Zone' in test mode and press the 'Execute Commands'
softkey.
3. Select the 'Detector test END' command.
The 'Zone' is switched to normal operation.
The yellow 'DETECTOR TEST' LED goes out.