5 Commissioning overview
The ↑ 'Stations' on the FCnet, such as control panels FC2020/FC2040 and fire
terminals FT2040 and FT2080, are connected to the power supply and
commissioned by the installation and commissioning personnel.
● Networked 'Stations' must only be commissioned with SintesoWorks.
● Standalone control panels can be commissioned with or without SintesoWorks.
NOTICE
Impermissible commissioning procedures result in faults during operation.
Only the procedures described in this document are permitted.
5.1 Commissioning variants
In order to satisfy Ordinance No. 305/2011 (the Construction Products Regulation –
CPR), the firmware of a newly installed fire detection installation must be current
market package version MP6 or higher.
NOTICE
Firmware version of a newly installed
fire detection installation not updated
No CPR conformity
● Compare the firmware version of a newly installed fire detection installation
with the firmware version MP6.
Update the firmware if necessary.
The table below provides an overview of the procedure for commissioning the
'Stations'. The letters A, B1, B2 and C refer to the detailed descriptions in the
following chapters.
Standalone control panel Networked 'Stations'
Without
SintesoWorks
No pre-
configuration
possible
A
● Auto-configuration
● Adaptations on the ↑ Person
Machine Interface
Not possible.
With
SintesoWorks
Without pre-
configuration
B1
● Auto-configuration
● Adaptations in SintesoWorks
C
● Initialize the 'Stations' for
networking
● Read in the FDnet devices by line
● Assign the logical elements to
SintesoWorks
With pre-
configuration
B2
● Read in the FDnet devices by line
● Assign the logical elements to
SintesoWorks
Table 1: Commissioning variants