Commissioning standalone 'Station' without PC
License
6
38 | 188
Building Technologies
009052_s_en_
--
Fire Safety
2016
-
-
02
6 A - Commissioning standalone 'Station'
without PC
The procedure in this chapter is only valid for
standalone '
Stations
'.
In this commissioning variant, a 'Station' without a PC and a SintesoWorks are
commissioned.
Prerequisites
The detector lines and FDnet devices are installed.
The acceptance test has been carried out for the detector lines.
The 'Station' is installed, but the batteries are not connected yet.
The cables for the detector lines and the mains supply have been inserted in
the 'Station', but not connected.
You will find additional information about the individual steps on the specified
pages.
Commissioning
1. If necessary, configure the power supply. Link [ 39]
2. Prepare the 'Station' for commissioning. Link [ 76]
3. Perform auto-configuration:
Auto-configure 'Station'. Link [ 79]
OR
Auto-configure detector lines individually. Link [ 79]
4. Adapt the auto-configuration in the Person Machine Interface, e.g.:
Changing customer texts. Link [ 39]
Set the parameter sets of the FDnet devices. Link [ 40]
5. Test the function of the 'Site' and remedy the problems, if any. Link [ 91]
6. Perform the completion tasks. Link [ 91]