15 Commissioning the control panel with MS9i
detector lines
Prerequisites
The 'Station' is installed, but the batteries are not connected yet.
The cables for the detector lines and the mains supply have been inserted in
the 'Station', but not yet connected.
SintesoWorks is installed on the PC.
The current firmware and BDV are available on the PC.
You will find additional information about the individual
steps on the specified
pages.
Commissioning steps
1. Create the pre-configuration of the MS9i detector line. You will find more
information in document 009078. See chapter 'Applicable documents'.
2. Prepare the 'Station' for commissioning – without BDV installation.
Link [ 77]
3. Connect the PC to the 'Station'. Link [ 27]
4. Load the configuration from the PC to the 'Station'. Link [ 30]
5. Test the function of the 'Site'. Link [ 91]
6. Remedy any errors you notice and load the corrected configuration from the
PC to the 'Station'. Link [ 30]
7. Disconnect the PC from the 'Station'. Link [ 27]
8. Perform the completion tasks. Link [ 91]