Commissioning standalone 'Station' with PC, without pre
7
41 |
Building Technologies
7 B1 - Commissioning standalone 'Station' with
PC, without pre-configuration
First auto-configure the ↑ 'Station' in this commissioning variant. Then adapt the
auto-configuration manually in SintesoWorks.
The procedure in this chapter applies exclusively to
only valid for FDnet detector lines.
Prerequisites
● The ↑ detector lines and FDnet devices are installed.
● The acceptance test has been carried out for the detector lines.
● The ↑ 'Station' is installed, but the batteries are not connected yet.
● The cables for the detector lines and the mains supply have been inserted in
the 'Station', but not yet connected.
● SintesoWorks is installed on the PC.
● The current firmware and ↑ BDV are available on the PC.
You will find additional information about the individual steps on the specified
pages.
Commissioning
1. Prepare the ↑ 'Station' for commissioning. Link [➙ 76]
2. Perform auto-configuration:
– Auto-configure 'Station'. Link [➙ 79]
OR
– Auto-configure detector lines individually. Link [➙ 79]
3. Connect the PC to the 'Station'. Link [➙ 27]
4. Load the automatically created configuration to the PC. Link [➙ 80]
5. Adapt the configuration in SintesoWorks. Link [➙ 80]
6. Load the configuration from the PC to the 'Station'. Link [➙ 30]
7. Test the function of the ↑ 'Site'. Link [➙ 91]
8. Remedy any errors you notice and load the corrected configuration from the
PC to the 'Station'. Link [➙ 30]
9. Disconnect the PC from the 'Station'. Link [➙ 27]
10. Perform the completion tasks. Link [➙ 91]