Commissioning B 3
ekrPro Com
60
web guide controller EDV No.: MD.191.01.05/1.6.x Chapter: B 3
with analog sensors Date: 23.11.2007 Page: 1/73
B 3 Commissioning
B 3.1 General information
The controller ekrPro Com
60
is matched to the actual configuration of
the control system (connected sensors, actuator, sensor adjustment
unit, ...) using the system parameters in the individual setup menus.
The required parameters have already been entered if the control
system is an integral part of a projected BST system. You do not
have to reset anything with regard to this.
A new system configuration is required if components or the
controller have been exchanged on-site.
The range of the settings and therefore the set-up menus that have
to be taken into consideration depend on the system being used.
To simplify commissioning, the commissioning staff can select his
system from a list of the most common standard systems (see
chapter B.3.5).
Following the selection, all of the basic settings are automatically
entered in the setup menu.
Finally the commissioning staff has only to check a few application-
related settings and if necessary adjust them accordingly.
The procedures to be used with the separate menus are described
in section B 3.7.5 General set-up.
Danger from mains voltage!
Never open the controller before switching off the
mains!