GE
P
ART NUMBER FN091065, REVISION 2 VS5 N AND VS6 N SERVICE MANUAL
Chapter 3 - System Setup 3-77
PRELIMINARY
6.) Proceed as follows:
a.) Loosen the screw to open the plastic cable clamp (see Figure 3-88).
b.) Route the AC power cable upwards and through the clamp.
c.) Screw the plastic cable clamp into position on the support column (see Figure 3-89), carefully
tightening the screw sufficiently to secure the cable firmly in the clamp.
Take care not to overtighten the screw, or damage the cable!
7.) Connect the other end (male plug) of the AC Power Cable to a hospital-grade mains power outlet
with the proper rated voltage.
8.) Turn ON the circuit breaker at the rear of the system.
The unit is now ready for Power ON/Boot Up. Refer to the instructions for ‘Turning the System ON”
on page 4-5.
.
Figure 3-88 Plastic Cable Clamp and Securing Screw
.
Figure 3-89 Mains Power Cable Secured with Plastic Cable Clamp
Screw hole for Securing
Plastic Cable Clamp
and Screw
Plastic Cable Clamp
Plastic Cable Clamp
Screw
AC Power Cable