8-108 Section 8-3 - Control Console Components Replacement Procedures
PRELIMINARY
opening and slide it upwards, as indicated in Figure 8-129.
12.)Re-connect the GND cable to the centre of the upper arm - see Figure 8-110.
13.)While moving the keyboard slightly up and down with one hand, push the securing pin into the base
of the operator panel (below the keyboard). If necessary, gently tap it into position using the handle
of a screwdriver. Refer to Figure 8-243 on page 8-194.
14.)Return the LCD arm lower cover to the arm (push and snap it into position) - refer to Figure 8-110.
15.)Return the LCD arm upper cover to the arm (push and snap it into position) - refer to Figure 8-109.
16.)Return and fasten the three Allen screws to the LDC metal mounting plate, as show in Figure 8-108.
17.)Return the Monitor, as described in “Monitor Installation Procedure” on page 8-29.
18.)Turn ON power to the system.
19.)Proceed to perform the following functionality tests:
- “Grounding Continuity” on page 10-23
- “Chassis Current Leakage Test” on page 10-24
- “Speakers Tests” on page 4-21
- “Alphanumeric Keyboard Test” on page 4-18
- “Extended Keyboard and Trackball Test” on page 4-18
- “Light Detector Test for Vivid S6 N only” on page 4-22
- “USB Test” on page 4-37
- “Monitor Test” on page 4-22