5. Install the four titanium washers and the four M6 bolts. Torque to 14 Nm
(10 ft.-lb). See Figure 19-21.
Figure 19-21 Install washers and bolts
IMPORTANT
For 8-drop Melt-CUBE systems with either a 40mm or a 50mm pitch, a side
clamp must be installed and torqued to 10 Nm (7.5 ft.-lb). See
Figure 19-22.
Figure 19-22 Install side clamp - specic systems only
6. Install the torpedo into the transfer seal. See Figure 19-23.
Figure 19-23 Install torpedo
Melt-CUBE Design B: Assemble the Melt-CUBE -
continued
19-27MELT-CUBE SYSTEMS
Hot Runner User Manual