19.4.9 Melt-CUBE Design B: Install Gate Seals and Cavity
Inserts
CAUTION
This procedure must be done with the Melt-CUBE at room temperature,
between 10°C and 40°C (50°F and 104°F).
CAUTION
1. Install the cavity insert into the cavity block.
Figure 19-24 Install cavity insert
2. Install the gate seal into the cavity insert. See Figure 19-25.
Figure 19-25 Install gate seal