Chapter 5 Maintaining Your Library
Maintenance Actions
Scalar i2000 User’s Guide 277
Test Descriptions 5
This section describes the verification tests that are available.
Installation Verification Test 5
The installation verification test enables you to verify that the library’s
installation and configuration is complete and functioning correctly. The
installation verification test runs the following individual tests:
• Library alignment test
•Picker assembly test
• I/E station assembly test
•Get/put test
• Scanner fiducial test
The smaller library configuration will require about 1 hour and the larger
configurations will require as long as 4 hours to run the installation
verification test. The time to complete individual tests on an eight-frame
configuration is approximately:
• Library alignment test - 30 minutes
• Picker assembly test - 1 minute
• I/E station assembly test - 5 minutes for each I/E station
• Get/put test - 120 minutes
• Scanner fiducial test - 75 minutes
Partial System Tests 5
The partial system tests perform the selected subtests to test an area or
range of the library configuration. The selectable tests include:
• Frame test - This test includes the same individual tests as the
installation verification test, but enables you to specify a range of
modules rather than testing all modules.
• Configuration test - This test includes the picker assembly and
scanner fiducial tests.
These times do not include debug or repair time.