EasyManua.ls Logo

GE MiCOM P747 Agile

GE MiCOM P747 Agile
458 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Test Result (mark where appropriate)
N/C Watchdog contacts closed? Yes / No
N/O Watchdog contacts open? Yes / No
Measured auxiliary supply ……………………..V DC / AC
1.5 TESTS WITH PRODUCT ENERGISED
General Tests Result (mark where appropriate)
N/C Watchdog contacts open? Yes / No
N/O Watchdog contacts closed? Yes / No
LCD contrast setting used ...............................
Clock set to local time? Yes / No
Time maintained when auxiliary supply removed? Yes / No
Alarm (yellow) LED working? Yes / No
Out of service (yellow) LED working? Yes / No
Programmable LEDs working? Yes / No
All opto-inputs working? Yes / No
All output relays working? Yes / No
1.6 COMMUNICATION TESTS
Communications Result (mark where appropriate)
SCADA Communication standard
(Courier, DNP3.0, IEC
61850, IEC 60870, Modbus)
Communications established? Yes / No
Protocol converter tested? Yes / No / N/A
1.7 CURRENT INPUT TESTS
Current Inputs (if applicable) Result (mark where appropriate)
Displayed current Primary / Secondary
Phase CT ratio (if applicable)
Input CT Applied Value Displayed Value
IA
IB
IC
IN
ISEF (if applicable)
Note:
Reuse the table for each CT tested.
Appendix B - Commissioning Record MiCOM P747
426 P747-TM-EN-1
P747-TM-EN-1.1

Table of Contents

Related product manuals