Table 13: High voltage three-phase PDU for Oracle Flash Storage Systems
(continued)
High Voltage 3Ph (5W + ground)
Maximum input current for each cord 25A
Outlet receptacles (number/type) 42/C13 (seven for each outlet group)
6/C19 (one for each outlet group)
Outlet groups for each PDU 6
PDU power cord length 2 meters (6.6 feet)
PDU power cords are 4 meters (13 feet)
long, but sections are connected for internal
routing in the rack.
Site Preparation Checklist (Not-racked Systems)
Before system installation, complete the tasks outlined in the pre-installation
checklist as part of the site preparation and installation planning. Your Oracle
Sales team can arrange for site audit and installation services.
Table 14: Site preparation checklist
Check Site preparation or pre-installation planning items
Pre-installation site preparation: Prior to system delivery, a site audit must be
conducted.
❑
Determine the suitability of access routes to the installation location, such
as carpet, doors, elevators, oor strengths, and ramps.
❑
Determine the load capacity of the oor where the system is to be
installed.
❑
Verify the cleanliness of the site and inform the customer to perform any
required cleaning.
❑
Note any problems or peculiarities at the site that require special
equipment.
❑
Determine if there will be raised oors, where the cabling will be under
the oor. For raised oors, cutout tiles with protected edges will be needed
prior to installation.
Oracle FS Systems: Installation Overview
28