Maintenance Commands
555-233-143
7-300 Issue 1 May 2002
BRI 0-126 L3-Assigned ext# yes This is a transitory state for BRI
endpoints that support MIM
initialization when a SPID Facility
test has been used to initialize the
station.
1. Wait 5 seconds and repeat the
command. If the state has not
changed continue with Step 2.
2. Make sure SPID administration
on the switch and endpoints are
consistent. Repeat status
bri-port to determine whether
the Layer 2 state of the
signaling link is
L3-Established. If it is
not, go to Step 3.
3. Try replacing the endpoint.
Repeat status bri-port to
determine whether the Layer 2
state of the signaling link is
L3-Established. If it is
not, follow normal escalation
procedures.
Table 7-45. Interpreting BRI-Port Status Reports — Continued
Error
Type
Aux
Data Associated Test
Alarm
Level
On/Off
Board Test to Clear Value
Continued on next page