FUEL SYSTEM 355
Figure 560 Installing the high-pressure oil rail
assembly
8. Lift high-pressure oil rail assembly up and place
onto engine. Align injector oil supply nozzles with
oil inlet adapters.
H08090
1
3
4
7
8
11
12
2
5
6
9
10
Figure 561 High-pressure oil rail bolt torque sequence (typical)
9. Install and hand tighten 12 bolts (M8 x 90) to
secure the high-pressure oil rail to the cylinder
head. Tighten bolts to the special torque value
(Table 47) and in the circular pattern, beginning
from the center.
EGES-265-2
Read all safety instructions in the "Safety Information" section of this manual before doing any procedures.
Follow all warnings, cautions, and notes.
© 2009 Navistar, Inc.

Table of Contents

Other manuals for Navistar INTERNATIONAL DT 466

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Navistar INTERNATIONAL DT 466 and is the answer not in the manual?

Navistar INTERNATIONAL DT 466 Specifications

General IconGeneral
BrandNavistar
ModelINTERNATIONAL DT 466
CategoryEngine
LanguageEnglish

Related product manuals