Commissioning
- 34 -
optek-converter C4101 Version 07.2009_1.2US, 23.07.2009
www.optek.com
8.4 Other activities when commissioning
1. Check the system's zero point in the converter software (either at the
converter in the MAINTENANCE menu chapter 9.11.2, page 135 or via the
control system chapter 9.12, page 164).
2. Enter the system settings (see chapter 9.4, page 43).
3. Enter the product settings (see chapter 9.5, page 51).
4. Document your settings using the form (see chapter 12.1, page 192).
5. Check measuring results with regard to plausibility.
6. If settings and measuring results are correct, enable measuring.