Installation
4-164 Service Manual
Installing the power supply
4.8.2 On the HiPath 1150
Installation Procedures
Figure 4-33 Installing the PSU HiPath 1150
Step Procedure
1. Check network voltage
2. Install the ferrite (C39022-Z7000-C7) in the AC power cable of the PSU at most 20
mm from the female connector (see Figure 4-35 on page 4-165).
3. If the voltage is within the power supply’s voltage range, connect the power supply.
4. If the power supply has a battery input socket (BBU) or if you have acquired the BBU
extension kit (S30817-H853-B401-*), please connect them as indicated in
“Installing the batteries” on page 4-169.
5. “Performing a visual inspection” on page 4-189
6. Configure the required data (see “Operation” on page 7-278).
Warning
Use the cable of the power supply to turn system power on or off. If batteries are
installed, they should also be turned on or off.
!