4.19 Performing a visual inspection
Introduction
Before starting up the system, perform a visual inspection of all hardware, cables and power
supply. This procedure should be performed with the entire system turned OFF.
.
.
Visual inspection procedure
Table 4-8 Visual inspection procedure
Warning
Check whether all AC and DC connections of the cables, modules and chassis of the
HiPath 1100 are correctly and properly connected before connecting the client inter-
face.
Warning
Before starting to work on the HiPath 1190, make sure the system is grounded and
disconnected from all power sources.
Follow all guidelines to protect the system from electrostatic discharge (see “Safety
Information: Caution” on page 1-21).
Step Procedure Help/
Notes
Measurements
1. Compare the installation position of
modules on the slots against the
installation diagram.
Module installation
diagram.
Make the appropriate
corrections
to the modules and notify
the person in charge.
2. Check to see that all modules are
securely and properly attached.
See “System Data”
on page 2-26.
Attach or secure modules
as needed.
3. Check the network’s line voltage. Multimeter. Verify voltage at power
source.
!
!