The device connection voltage entered in the "Network data" dialog is displayed: This is the
basis for monitoring the
supply voltage (p0281 - p0283) for the alarm threshold and shutdown
threshold.
Figure 5-3 S120 Combi infeed (page 2)
5.1.4 Example: This is how you configure the spindle (DO3)
Configuring the spindle
The spindle (drive object DO3) must be manually commissioned, because it is not operated
with an SMI motor. As a consequence, the motor and measuring systems cannot be
automatically determined.
Commissioning the drive
5.1 Commissioning the drive
CNC commissioning
Commissioning Manual, 10/2015, 6FC5397-3DP40-5BA3 99