12E5119 Instruction Manual QuickTOC
®
ultra
IECEx 53
4 Installation
4.3 Mounting and Installation of the Analyser On-site
LAR | PROCESS ANALYSERS AG
4.3.2 Wall Mounting
Observe the following mounting dimensions:
At least 1.430 x 1.760 x 1.210 mm (W x H x D)
Fig. 35: Wall mounting
Warning
Improper Mounting!
The distance to side and opposing walls must be kept so that the analyser can
be opened.
Take into account the condition of the wall to which the analyser is to be af-
fixed. The wall should have the solidity of a concrete wall. Gas concrete walls
are unsuitable!
Use all of the brackets (M1 - M4) of the analyser for installation.
Ensure that the analyser is aligned horizontally. Use a spirit level for levelling.
M1
M2
M3
M4
!