12E5119 Instruction Manual QuickTOC
®
ultra
IECEx 57
LAR | PROCESS ANALYSERS AG
5 Start-up
5 Start-up
This section provides all information about the start-up of the analyser. The following start-up procedure
serves as an overview. The start-up must be carried out properly and documented by Technical Support
of LAR or by another person authorised by LAR, .
5.1 Procedure
The start-up procedure is divided into start-up of the analyser and start-up of accessories.
5.1.1 Start-Up of the Analyser
1. Checking the Pre-Fusing (Chapter 5.2 on page 59)
2. Checking the Installation Plate (Chapter 5.3 on page 59)
3. Remove Transportation Locks (Chapter 5.4 from page 59)
4. Align the Voltage (Chapter 5.5 on page 62)
5. Switch on the Fuses (Chapter 5.6 on page 62)
6. Filling and Installation of the Reactor Pipe (Chapter 5.7 from page 63)
7. Completing the Furnace System (Chapter 5.8 on page 65)
8. Installation of the Glass Components (Chapter 5.9 on page 67)
9. Installation of the Pump Tubes (Chapter 5.10 from page 68)
10. Tubing of the Analyser (Chapter 5.11 on page 70)
11. Electrical Connection of the Control Unit and the Relays (Chapter 5.16 on page 76)
12. Connection of the Emergency Cooling for the Furnace (Chapter 5.13 on page 72)
13. Switching on the Analyser (Chapter 5.14 on page 73)
14. Set Bypass of the Control Unit (Chapter 5.15 on page 74) and switching into the bypass mode.
15. Test Run (Chapter 5.16 on page 76)
16. Rinse the Injection System and Sample Tubes (Chapter 5.17 on page 76)
17. Customization of application specific Settings (Chapter 5.18 on page 76)
18. Checking the Status Parameters (Chapter 5.19 on page 76)
19. Perfom a Calibration (Chapter 5.20 on page 77), and, if necessary, perform a second calibration
5.1.2 Start-up of Options
• Start-Up of the Reagent Cabinet (Chapter 9.2.3 on page 208)
• Start-Up of the FlowSampler
®
(Chapter 9.3.5 from page 221)
Warning
Warning of improper start-up
Do not switch on the analyser before start-up without having completed the installation
(described in the previous chapter) and without the presence of a technician authori-
sed by LAR - because this voids the warranty of your analyser.
!