58 Instruction Manual QuickTOC
®
ultra
IECEx 12E5119
5 Start-up
5.1 Procedure LAR | PROCESS ANALYSERS AG
Table 7: Start-up protocol for the analyser
Task Criteria OK Comment
Checking the Pre-Fuses • Pre-Fuse is installed correctly
Checking the Installation
Plate
• Components are fixed
Remove Transportation
Locks
• Furnace Transport Screw is
removed
• Cable tie at XY-System is
removed
Align the Voltage • Voltage is correct
Switch on the Fuses
• Fuse Lock is removed
• All Fuses are switched on
Filling and Installation of the
Reactor Pipe
• Reactor Pipe is filled
• Reactor Pipe is installed
Completing the Furnace
System
• Furnace Head is installed
• Injection Port is installed
• Reactor Foot is installed
Installation of Glass
Components
• Glass Components are mounted
Tubing of the Analyser
• Tubing is performed like in Flow
Diagram
• Tubes are hand-screwed onto
the screwed joints
Electrical Connection of the
Control Unit and the Relays
• Control Unit and Relays are
connected
Connecting the Emergency
Cooling of the Furnace
• Emergency Cooling of the
Furnace is connected
Switching on the Analyser • Analyser is switched on
• Analyser is booted
Set bypass of the Control
Unit and switching into the
bypass mode
• Bypass for the Control Unit is set
and Bypass mode is ON
Test Run • All Positions are hit
Rinse the Injection System
and Sample Tubes
• Injection System and Sample
Tubes are rinsed
Customization of application
specific Settings
• Hardware and Parameter
Settings are set
Checking the Status
Parameters
• Carrier Gas IN / OUT: approx.
30 l/h (High Salt: approx. 20 l/h)
• Humidity: Actual < Target
• Gas Pressure: Actual < Target
• Zero Signal: 0 - 0.1 FSR
Perfom a Calibration • Analyser is calibrated
Start the Measuring Mode • Measuring Mode works just fine
If necessary, perfom a
second Calibration
• Analyser is calibrated
Date: Signature: