EasyManua.ls Logo

Siemens 6MD86 - Functional Measured Values

Siemens 6MD86
1256 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Connect the LN
Trafo1\VCtrl1\ATCC1
of the device to the function and the other LN
Trafo2\Ctrl_90VParallelOperation\ProxyATCC1
to the proxies according to Figure 6-156.
Step 5
Create a new GOOSE application and subsequently perform the GOOSE later binding using the applica-
tion template. With the GOOSE application template, all the links between the devices and the proxies
are automatically connected.
Set all the settings for GOOSE communication between the Master and the Follower devices in the
IEC 61850 System Configurator.
If you have done all the links and settings in the IEC 61850 System Configurator, save the project and
close the IEC 61850 System Configurator.
[sc_parasyscon_goose, 1, en_US]
Figure 6-157 Creating the GOOSE Application
Step 6
Import the SCD file generated and stored in the IEC 61850 System Configurator back to DIGSI.
[sc_para_import, 1, en_US]
Figure 6-158 Import from the IEC 61850 System Configurator into DIGSI
Load the created configuration to the devices.
Functional Measured Values
You can read the current status of the measured values for the two-winding transformer, the parallel control/
proxy, the three-winding and grid coupling transformer at any time. The following tables show you the avail-
able measured values.
6.9.3.10
Control Functions
6.9 Voltage Controller
484 SIPROTEC 5, High-Voltage Bay Controller, Manual
C53000-G5040-C015-9, Edition 11.2017

Table of Contents

Other manuals for Siemens 6MD86

Related product manuals