192 Upgrade and Maintenance Manual RX900 S2
Main memory
© cognitas. Gesellschft für Technik-Dokumentation mbH 2011 Pfad: C:\Programme\FCT\tim_app\tim_local\work\WALTER\OBJ_DOKU-12051-001.fm
9.3.2 Starting the task
Ê Perform the following procedures:
1. "Opening the rack door" on page 40
2. "Shutting down the server" on page 41
3. "Sliding the server out of the rack" on page 42
4. "Opening the server" on page 44
5. "Removing the CPUMEMR" on page 190
9.3.3 Selecting the DIMM memory module slot
Ê Choose the DIMM memory module slot according to the configuration rules
summarized in this section. For detailed information see "Baseboard D3144,
CPUMEMR D3145, PCIR D3146 for PRIMERGY RX900 S2 Technical
Manual".
CPUMEMRs are populated in four steps. In each step, four DIMM memory
modules are added. At least four DIMM memory modules must be installed on
CPUMEMR #1 and #2. CPUMEMRs #3 to #8 can be left empty. figure 113 and
table 5 show the population order for DIMM memory modules.

Table of Contents

Other manuals for Fujitsu PRIMERGY RX900 S2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fujitsu PRIMERGY RX900 S2 and is the answer not in the manual?

Fujitsu PRIMERGY RX900 S2 Specifications

General IconGeneral
BrandFujitsu
ModelPRIMERGY RX900 S2
CategoryServer
LanguageEnglish

Related product manuals