To flush the melter and test the system
1.. Add adhesive to the adhesive bin.
2.. Touch Master Controls > Refill to enable the fill system.
Grid
175C
Manifold
175C
Zone 1B
175C
Zone 2B
175C
Zone 3B
175C
Zone 4B
175C
Zone 1A
175C
Zone 2A
175C
Zone 3A
175C
Zone 4A
175C
Master
Controls
Pump: On
Heaters: On
Password: Disabled
Recipes:
Nothing Loaded
Fill Status
Pump
Ready
System Status:
Ready/OK
Ready
Done
Scheduler
Pump Control
Heater Control
Standby
Settings System
Scheduler: On
Pump: OnHeaters: On
Standby: Off
Refill
Enabled
Master Controls
Ready
Figure 4‐35 Enabling the fill system
3.. Wait for the system to fill the melter with adhesive and to reach
Ready/OK status.
NOTE: At initial startup, the system requires more than one cycle to fill.
Although this is normal, a fill warning may be generated. Acknowledge
the warning and reset the system, thus initiating another fill cycle after a
short delay. It can take several fill cycles to satisfy the level sensor. After
the melter is properly filled, the system will work normally to maintain the
proper adhesive level.