Installation
3-20
Part 1123087_02
3/2014 Nordson Corporation
Configure the Electrical Service (contd)
See Figure 3‐16.
3. Strip approximately 15 cm (6 in.) of jacketing from the power cord and
route it through the cable clamp (3).
NOTE: If maximum protection from splashed liquids is required, Nordson
Corporation recommends the following:
Use liquid‐tight conduit and fittings, or
If a jacketed, multi‐cable conductor is used, replace the supplied
cable clamp with a liquid‐tight cable clamp
4. Connect each lead to terminal block XT1 (2) on the expansion board (1).
Table3‐2 lists the terminals that are used for each of the electrical
service types that are compatible with the melter.
5. Connect the ground lead from the power cable to the ground
connection(4) on the chassis. The ground lug is marked PE/G.
Table 3‐2 Electrical Service Information
If the Electrical Service Type is..
Use Electrical Connector
Terminals..
Use Voltage Plug..
L1 L2 L3 N
400/230 VAC 3-phase
(4-wire service, including a
neutral) See note.
3/N/PE AC
400/230 V
227569
Red/Yellow
230 VAC 1-phase
(2-wire service, including a
neutral) See note.
1/N/PE AC
200−240 V
232617
Blue/Yellow
200 to 240 VAC 3-phase
(3-wire service without a
neutral)
3/PE AC
200−240 V
227568
Red/Green
200 to 240 VAC 1-phase
(2-wire service without a
neutral)
1/PE AC
200−240 V
227567
Blue/Green
NOTE: The 400/230 VAC 3-phase service (4-wire service including neutral) includes the 415/240 VAC 3-phase (4-wire service,
including neutral) voltage. The 230 VAC 1-phase service (2-wire service, including a neutral) includes the 240 VAC 1-phase (2-wire
service, including a neutral) voltage.