6-2
Chapter 6 4100ES SPS Field Wiring
General Field Wiring Guidelines
General
Guidelines
Make sure these guidelines are accounted for before wiring:
All wires must be 18 AWG, or as the local code dictates.
Conductors must test free of all grounds.
All wiring must be done using copper conductors only, unless noted otherwise.
If shielded wire is used,
- the metallic continuity of the shield must be maintained throughout the entire cable length.
- the entire length of the cable must have a resistance greater than 1 Megohm to earth ground.
Underground wiring must be free of all water.
In areas of high lightning activity, or in areas that have large power surges, the 2081-9027 Transient
Suppressor should be used on monitor points.
Wires must not be run through elevator shafts.
Wires that run in plenum must be in conduit.
Splicing is permitted. All spliced connections must either be soldered (resin-core solder), crimped in
metal sleeves, or encapsulated with an epoxy resin. When soldering or crimped metal sleeves are
used, the junction must be insulated with a high-grade electrical tape that is as sound as the original
insulating jacket. Shield continuity must be maintained throughout.
A system ground must be provided for earth detection and lightning protection devices. This
connection must comply with approved earth detection per NFPA780.
Only system wiring can be run together in the same conduit.