737 Flight Crew Operations Manual
Normal Procedures -
Amplified Procedures
Boeing Proprietary. Copyright © Boeing. May be subject to export restrictions under EAR. See title page for details.
D6-27370-866-EGP NP.21.29
failure of the ENGINE START switch to stay in GRD until the
starter cutout RPM can cause a hot start. Do not re–engage the
ENGINE START switch until engine RPM is below 20% N2.
If a fluid leak (other than a continuous stream) from any of the
engine drains is discovered during the Exterior Inspection, the
engine can be started. If during engine start, the ground crew
reports a fluid leak from an engine drain, the engine start may be
continued. In either case, run the engine at idle thrust for up to 5
minutes. If the fluid leak stops during this time, no maintenance
action is needed. If the fluid leak continues after 5 minutes, shut
down the engine for maintenance action.
For the first flight of the day, at airport elevations at or above 2,000
feet MSL, if the temperature is below 5°C/41°F, consider placing
the Ignition select switch to BOTH before starting the engines.
This may increase the likelihood of a successful engine start on the
first attempt.
Do the ABORTED ENGINE START checklist for one or more of the
following abort start conditions:
the N1 or N2 does not increase or increases very slowly after the
EGT increases
there is no oil pressure indication by the time that the engine is
stable at idle
the EGT does not increase by 10 seconds after the engine start lever
is moved to IDLE detent
the EGT quickly nears or exceeds the start limit
Select the secondary engine indications. F/O
Air conditioning PACK switches...................................OFF F/O
Start sequence .......................................................Announce C
Call “START ___ ENGINE” C
ENGINE START switch ...............................................GRD F/O
Verify that the N2 RPM increases. C, F/O
When N1 rotation is seen and N2 is at 25%, or (if 25% N2 is not
possible), at maximum motoring and a minimum of 20% N2:
Note: Maximum motoring occurs when N2 acceleration is less
than 1% in approximately 5 seconds.
Engine start lever ....................................IDLE detent C
Monitor fuel flow and EGT indications. C, F/O