GEDRAFT LOGIQ P9/P7
D
IRECTION 5604324, REVISION 11 DRAFT (JANUARY 24, 2019) SERVICE MANUAL
Chapter 8 - Replacement Procedures 8-153
Section 8-30
Replacement of the Probe Holder
8-30-1 Manpower
1 Person, 5 minutes.
8-30-2 Tools
No tool is required.
8-30-3 Removal Procedure
1) Simply pull out Probe Holder from its location.
NOTE: This procedure applies to all locations of probe holder.
Figure 8-180 Removal of Probe Holder
Figure 8-181 Probe Holders
8-30-4 Installation Procedure
Parts to be installed in reverse order of removal.
8-30-5 Functional Check
Visual inspection Only.