EasyManuals Logo

KAESER SIGMA CONTROL 2 User Manual

KAESER SIGMA CONTROL 2
246 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #183 background imageLoading...
Page #183 background image
1. Check and confirm all the items in the check list before commissioning the machine.
When power is applied to the machine the controller boots and carries out a self test.
The display and the
Controller on
LED illuminate.
8 8 p s i 0 8 : 1 5 A M 1 7 6 ° F
Header
------------------------------
Load
Current operating mode
------------------------------
Key – on ¦ pA – on
Operating parameters
------------------------------
Run 2500h Load 2490h
Operating parameters
Maintenance in 500h
Maintenance indicator
2. Continue the commissioning process as described in chapter "Commissioning" of the ma‐
chine's operating manual.
8 Initial Start-up
8.15 Commissioning the machine
No.: 9_9450 13 USE
User Manual Controller
SIGMA CONTROL 2 SCREW FLUID ≥5.1.2
173

Table of Contents

Other manuals for KAESER SIGMA CONTROL 2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the KAESER SIGMA CONTROL 2 and is the answer not in the manual?

KAESER SIGMA CONTROL 2 Specifications

General IconGeneral
Controller TypeMicroprocessor-based
ModelSIGMA CONTROL 2
ManufacturerKAESER
Input Voltage24 V DC
Protection ClassIP54
Communication ProtocolsModbus, Profibus
Data LoggingComprehensive data logging
Remote MonitoringYes
Communication InterfaceEthernet