1. Check and confirm all the items in the check list before commissioning the machine.
When power is applied to the machine the controller boots and carries out a self test.
The display and the
Controller on
LED illuminate.
8 8 p s i 0 8 : 1 5 A M 1 7 6 ° F
Header
------------------------------
Load
Current operating mode
------------------------------
Key – on ¦ pA – on
Operating parameters
------------------------------
Run 2500h Load 2490h
Operating parameters
Maintenance in 500h
Maintenance indicator
2. Continue the commissioning process as described in chapter "Commissioning" of the ma‐
chine's operating manual.
8 Initial Start-up
8.15 Commissioning the machine