Push in the lock on the left side (1) and remove the front cover in a slight
angle from the front (2).
4.3
Shutting down the server
CAUTION
▶
For more information, see "Important information" on page
33.
This step is only required when upgrading or replacing non-hot-plug
components.
▶
Inform the system administrator that the server will be shut down and put
of
fline.
▶
Terminate all applications.
▶
Perform the required procedures described in the preliminary steps of each
upgrade or maintenance task.
▶
Shut down the server.
If the system is running an ACPI-compliant operating system (OS),
pressing the On/Off button will perform a graceful shutdown.
4.4 Disconnecting the power cord
4.4.1
Disconnecting the power cord (AC PSU)
You can secure the power cord with a cable clamp or a hook-and-loop
tape to ensure that the power cord cannot be disconnected from the
server by mistake.