Figure 20: Connecting the server to the DC voltage - example DC PSU -48 V
Connect the power cord to the PSU (1).
Fasten the two studs (2).
Ensure that the status indicator on the PSU is lit green, see "Indicator on
hot-plug PSU" on page
553.
If necessary, make a permanent connection to the distribution board.
CAUTION
If the server/rack is intended for permanent connection to the mains only
an authorized specialist (electrician) is allowed to work.
Please follow the regulation of each country.
It will take about 60 seconds until the server can be switched on.