16.2.1 Commissioning
During commissioning, the EtherCAT master operates as gateway to access from the Engineer-
ing PC t
o the slaves.
In the following, the required steps are described to control the device as EtherCAT slave.
Precondions
The in
verter is networked as EtherCAT slave to an EtherCAT master and, if necessary, fur-
ther EtherCAT devices.
See "Typical topologies" under: 4EtherCAT ^ 334
The enre wiring has already been checked for completeness, short circuit and earth fault.
All E
therCAT devices are supplied with voltage and are switched on.
An Engineering PC with installed »PLC Designer« is connected to the master.
Download »PLC Designer«
A »PLC Designer« project with current device descripon les for EtherCAT is available.
Download XML/ESI les for Lenze devices
The les are installed via the device repository of the »PLC Designer« (menu command
"Tools à Device repository").
Conguring the network