4.4 Commissioning
Pr
erequisites
•
The mechanic
al and electrical installaon of the inverter is complete.
•
If necessar
y, the motor is mechanically decoupled from the system.
•
Check whether the system can be mechanically damaged if the non-decoupled drive
makes uncontrolled movements.
•
The connecon between the inverter and the engineering PC with instal-
led »EASY Starter« has been established.
•
The »EASY Starter« is open and connected to the inverter.
•
The inverter is supplied with voltage.
•
For parameterisaon purposes, it makes sense to supply the device with 24 V if the
mains voltage and the motor data deviate from the default seng. 4Funcon assign-
ment of the inputs and outputs (default seng) ^ 37
•
If it has been ensured that the mains voltage and motor data sengs correspond to
the real condions , the mains voltage can be connected.
•
The device list of the »EASY Starter« contains the inverter with the correct device descrip-
on.
•
Addional informaon on the device descripon can be found in the chapter dealing
with conguraon of the respecve eldbus network. 4Conguring the network ^ 315
•
For an explanaon of where the device list can be found, please consult the online help
of the »EASY Starter«. Press the F1 key to call up the online help.
•
No fault is indicated by the inverter diagnoscs.
•
Check the LED s
tatus displays.
•
Check the error messages.
•
Check available applicaon credit on the storage medium.
Commissioning
The ve main commissioning steps are shown in order towards the top of the Sengs tab.
Clicking on a link displa
ys a corresponding interface containing the most important parameters
that need to be set.
4Gener
al informaon on parameter seng ^ 31
Commissioning step Descripon of the sengs
Basic
sengs The basic sengs are sucient for drive rotaon .
•
Check every preset parameter value to determine whether it can be retained for the applicaon.
•
If a v
alue has to be changed, click the cross-reference highlighted in blue to which the parameter is assigned. A new
interface opens. Here, the relevant value can now be changed.
•
Once all parameters have been correctly set in the basic sengs, you can allow the drive to rotate .
Communicaon These commissioning steps are for adjusng the drive and only have to be adapted where necessary.
•
Basic
sengs of the technology applicaon for adjusng the motor end and load side (gearbox rao, mounng
direcon, moments of inera, etc.)
•
Basic sengs of the technology applicaon for adjusng the moon control.
•
Sengs for adjusng the technology applicaon for the applicaon.
Kinemacs
Moon
Technology applicaon
Aer
adjusng the parameters: 4Saving the parameter sengs ^ 36
Seng and transferring safety parameters
Safety-relevant parameters only have to be set for devices that feature integra-
t
ed safety engineering or safety modules.
Observe the online help informaon on the safety parameter list.
In »EASY Starter« and »PLC Designer«, safety parameters can only be set and transferred using
the sa
fety parameter list. When a device featuring integrated safety engineering or a safety
module is selected in the device list, the safety parameter list becomes available in the form
of an addional tab.
Commissioning
Commissioning
35