Processors
11.2 Upgrading to dual processor configuration
V CAUTION!
– Processors are modules which are extremely sensitive to
electrostatic discharges and therefore must always be handled with
care. After a processor has been removed from its protective sleeve
or from its socket, place it with its smooth side down on a non-
conducting, antistatic surface. Never push a processor over a
surface.
– Only processors of the same type may be used on the system board.
That means the number of the internal processor cores as well as the
primary clock and the QPI frequency have to be the same.
– For dual operation, use a suitable multiprocessor operating system.
11.2.1 Preliminary steps
Ê "Disabling SVOM boot watchdog functionality" on page 64
Ê "Disabling BitLocker functionality" on page 63
Ê "Shutting down the server" on page 46
Ê "Disconnecting the server from the mains" on page 47
Ê "Getting access to the component" on page 47
Ê "Removing the air duct" on page 62
Field Replaceable Unit
(FRU)
Hardware: 15 minutes
Software: 5 minutes
Tools: Phillips PH2 / (+) No. 2 screw driver