1. PREPARATORY PROCEDURES FOR MONITORING
1.6 Checking for Normal Monitoring
Checking the wiring state (For optical loop system only)
Check if the optical fiber cable is connected correctly in [Loop test] of GX Developer.
For the GX Developer operation method, refer to the following manual.
Q Corresponding MELSECNET/H Network System Reference Manual (PLC to PLC network)
(1) Check the [Receive direction error station] (The display example on GX Developer Version 8)
GX Developer [Diagnostics] [MELSECNET (II)/10/H diagnostics]
Startup procedure
Loop test