Hardware
193
Cooling Fan
Unmount
Replace the cooling fan when it failed.
Pulling Out Server from Rack
Mount/Unmount the cooling fan with the server being pulled out from the rack.
1. Refer to“Preparation for Mounting/Unmounting” for preparation.
2. Install the stabilizer to prevent from falling to the front bottom of the rack.
3. Loosen four screws (circled in red shown below) on each front end.
Observe the following instructions to use the server safely.
There are risks of fire, personal injury, or property damage.
Refer to descriptions after page iii for details.
Do not get your fingers caught.
High temperature
Do not mount the server when the rack is unstable.
Pull out the stabilizer installed at the front bottom of the rack.
Do not leave multiple servers being pulled out from the rack.
CAUTION