Operation and Maintenance
645
13. Check test status.
Enter <stat> on the command line of the System Diagnostics screen to check the
executing status of the test.
The following is an example of screen using the command.
· Status: one of the following three statuses is displayed. This status is the status of TeDoLi
itself.
Idle status : Status before starting the test. Or the status after
the completion of test.
Executing status : Status that the test is being executed.
Waiting for Termination
status
: Status that waiting for the completion of the test.
· Time: elapsed time of the test being executed (elapsed time from entering <exec> command)
is displayed. The time is updated until all the tests are completed.
· Total of tests shows the total number of tests. Test types are sorted as follows depending on
the executed test results.
Pass: : Number of tests ended normally
Failure : Number of tests ended with error
Warning : Number of tests ended with warning (# This is an information expanded
in the future and is not supported as of yet).
· Use <statv> command to check the detailed status (number of executed times and progress
of each time) for each test.
· Test status can also be checked by using <list> on the test device list.
· Use <term> command to terminate the current test forcibly.
,Refer to Command List for more details on each command.
TeDoLi> stat
Status : Executing
Time : 000:00:44
Total of tests : 15
Running : 15
Pass : 0
Failure : 0
Warning : 0
TeDoLi> statv 16
----------------------
BM/MB/PCI8/Port1(eth0)
----------------------
Test Count : 74
Progress : 49%