Table 15: Site Preparation Checklist (continued)
DatePerformed ByFor More InformationItem or Task
“AC Power Specifications for a
QFX3500 Device” on page 166
Calculate the power consumption and
requirements.
Rack or Cabinet
“Rack Requirements for a QFX3500
Device” on page 114
“Cabinet Requirements for a
QFX3500 Device” on page 119
Verify that your rack or cabinet meets the
minimum requirements for the installation
of the device.
“Clearance Requirements for Airflow
and Hardware Maintenance for a
QFX3500 Device” on page 125
Plan rack or cabinet location, including
required space clearances.
Secure the rack or cabinet to the floor and
building structure.
Cables
“Determining Interface Support for
the QFX3500 Device” on page 141
Determining Transceiver Support for
QFabric Systems
“Cable Specifications for Console
and Management Connections for
the QFX Series” on page 146
Acquire cables and connectors:
Determine the number of cables
needed based on your planned
configuration.
Review the maximum distance allowed
for each cable. Choose the length of
cable based on the distance between
the hardware components being
connected.
Plan the cable routing and management.
RELATED DOCUMENTATION
General Safety Guidelines and Warnings | 203
General Site Guidelines
Installing and Connecting a QFX3500 Device | 326
Mounting a QFX3500 Device in a Rack or Cabinet | 328
96

Table of Contents

Related product manuals