3A-26 - ENGINES 90-823225--1 1096
4. Carefully install manifold assembly and torque
bolts to 35 lb. ft. (48 N·m) in sequence as shown.
72327
Intake Manifold Torque Sequence
1
2
3
5
6
7
8
9
10
11
12
4
5. Connect all electrical leads.
6. Connect hoses to thermostat housing.
7. Install fuel line and sight tube to carburetor and
fuel pump.
8. Connect crankcase ventilation hoses to rocker
arm covers.
9. Install distributor. Position rotor and housing to
align with marks made during removal, then in-
stall distributor cap.
10. Install other ignition components and reconnect
wires.
11. Coat threads of oil pressure sending unit with
Quicksilver Perfect Seal and install.
12. Connect any other items which were discon-
nected from manifold during removal.
13. Start engine. Adjust ignition timing and carbure-
tor. Check hose connections, gaskets and seals
for leaks.
14. Inspect fuel line connections for fuel leaks.
GEN+ ENGINES
IMPORTANT: When installing intake manifold
gaskets, in next step, be sure to do the following:
1. Apply a 3/16 in. (5 mm) wide bead of Quicksilver
RTV Sealer to engine block as shown. Extend
sealer 1/2 in. (13 mm) up on intake gaskets.
2. Apply Loctite Pipe Thread Sealant to the threads
of the four inner manifold bolts.
72325
a
a
b
b
a - 3/16 Bead Of RTV Sealer
b - Apply Loctite Pipe Thread Sealant
IMPORTANT: DO NOT get Quicksilver RTV Sealer
into oil sending unit hole at rear of engine.
72326
a - Oil Sending Unit Hole
a