8 Production
8.1 General notes
All filling functions are only supported by the "EasyFill" application.
NOTICE
Data is lost if the power is interrupted.
There are hard drives for 10 material data records available, which are retained after a
power failure.
It is important to save material data.
8.2 Configuration using the front-panel keys
The production parameters can be configured directly using the front-panel keys.
8.2.1 Configuring production mode using the front-panel keys
You can select between the following production modes:
- Net filling (B1)
- Net Discharge (B4)
Note:
See also Chapter
8.4.1.
1. Press .
SEtuP appears on the display.
2. Press OK.
The "Cd" calibration menu flashes.
Cd 000 appears on the display.
3. Press multiple times to select "CA 150."
4. Press OK.
dModE appears on the display.
5. Press OK.
nE.t (Net filling, B1) appears on the display.
6. Press if necessary, to select "ne.t d.l." (net discharge, B4).
7. Press "Exit" to exit the Setup menu.
8 Production X3 Process Indicator PR 5410
Minebea Intec EN-269

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Minebea Intec X3 and is the answer not in the manual?

Minebea Intec X3 Specifications

General IconGeneral
BrandMinebea Intec
ModelX3
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals