CHAPTER 6
Preparation Overview
•
Site Preparation Checklist for an EX9208 Switch on page 79
•
Environmental Requirements and Specifications for EX Series Switches on page 81
•
General Site Guidelines on page 85
•
Site Electrical Wiring Guidelines on page 86
•
Rack Requirements on page 87
•
Cabinet Requirements on page 87
•
Clearance Requirements for Airflow and Hardware Maintenance for an EX9208
Switch on page 88
Site Preparation Checklist for an EX9208 Switch
The checklist in Table 36 on page 79 summarizes the tasks you need to perform to prepare
a site for installing an EX9200 switch.
Table 36: Site Preparation Checklist
Date
Performed
byFor More InformationItem or Task
Environment
“Environmental
Requirements and
Specifications for EX Series
Switches” on page 81
Verify that environmental factors
such as temperature and humidity
do not exceed switch tolerances.
Power
Measure distance betweenexternal
power sources and switch
installation site.
79Copyright © 2017, Juniper Networks, Inc.