Note:
See Chapter 12.2
Example:
The gross weight should be read.
I/O size = 8 bytes, counted from byte 0–7
7.18.5.2 DeviceNet settings for Rockwell workstation
Requirements:
- PR 1721/34 DeviceNet is installed.
- The parameters are selected and saved.
Procedure:
Note:
See Chapter
12.2
Example:
The gross weight should be read.
I/O size = 8 bytes, counted from byte 0–7
7.18.5.3 ProfiNet I/O settings for S7
Requirements:
- PR 1721/36 ProfiNet I/O is installed.
Procedure:
NOTICE
Potential network problems
A unique device name must be assigned for the hardware configuration and
assignment/download.
1. Register the file "sag_5410.eds" using the "Hardware Installation Tool".
2. Select and insert the instrument from the catalog into the I/O configuration.
1. Establish communication with the PLC (here: SIEMENS S7-300/400 or S7-1500).
2. Enter the IP address and network mask under
- [Fieldbus parameter] and
confirm.
3. Add the PR 5410 device to the project and assign the I/O ranges.
X3 Process Indicator PR 5410 7 Getting started
EN-242 Minebea Intec