Shutting Down the Subsystem
There are two methods for shutting down the subsystem. Choose one of the
following procedures:
Shutting down the VTrak – Telnet Connection (page 241)
Shutting down the VTrak – SSH Connection (page 241)
Shutting down the VTrak – Serial Connection (page 242)
Shutting down the VTrak – Telnet Connection
This function shuts down the VTrak subsystem on a Telnet connection. Additional
action is required, as described below.
To shutdown the RAID subsystem:
1. From the Main Menu, highlight Additional Info and Management and press
Enter.
2. Highlight Shutdown or Restart and press Enter.
3. Highlight Option and press the spacebar to display Shutdown.
4. Highlight Submit and press Enter.
A warning message appears.
5. Press Y to continue.
The screen goes blank.
6. Wait for no less than two minutes.
7. Manually turn off the power supply switches on the back of the subsystem.
Shutting down the VTrak – SSH Connection
This function shuts down the VTrak subsystem on a SSH connection. Additional
action is required, as described below.
Important
If you have a JBOD Expansion, always power off the RAID
subsystem first. Then power off the JBOD subsystems.
Important
If you have a JBOD Expansion, always power off the RAID
subsystem first. Then power off the JBOD subsystems.

Table of Contents

Other manuals for Promise Technology VTRAK E610f

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Promise Technology VTRAK E610f and is the answer not in the manual?

Promise Technology VTRAK E610f Specifications

General IconGeneral
BrandPromise Technology
ModelVTRAK E610f
CategoryStorage
LanguageEnglish

Related product manuals