TLS-450 Setup and Operation Screens Manual
108
Pumps and Lines Setup - All PLLD
This tab screen lets you setup test parameters for all Pressurized Line Leak Detectors (requires PLLD
option).
Line Re-Enable Method
Allowable selections: Pass line test, Alarm acknowledge
Default: Pass line test
Periodic Test Needed Warning
Periodic Test Needed Warning, when enabled, informs you that a line will soon be out of compliance
because a Periodic test has not completed within the required time. The Periodic Test Warning lets you
take action (shut down the line) to see that a Periodic test is completed.
Allowable selections: Disabled, Enabled
Default: Disabled
Days Before Periodic Warning
Allowable selections: 0 - 30 days
Default: 25 days