3 - 2 Section 3-2 - Installation Reminders
Section 3-2
Installation Reminders
3-2-1 Average Installation Time
3-2-2 Installation Warnings
Table 3-2 Average Installation Time
Description
Average
Installation
Time
Comments
Unpacking the scanner 0.5 hour
Install Scanner wo/options 4 hours Dependent on the configuration
DICOM Network Configuration 2 hours Dependent on the configuration
DANGER
WHEN USING ANY TEST INSTRUMENT THAT IS CAPABLE OF OPENING THE
AC GROUND LINE (I.E., METER’S GROUND SWITCH IS OPEN), DON’T TOUCH
THE UNIT!
CAUTION
If the unit is very cold or hot, do not turn on its power until it has had a chance to acclimate to
its operating environment.
Table 3-3 Vivid 7 Acclimate Time
DON’T STORE AT
THESE
TEMPERATURES
KEEP STORAGE TEMPERATURE WITHIN THESE LIMITS
o
C
-40-35-30-25-20-15-10-5 0 5 1015202530354045505560
o
F
-40 -31 -22 -13 -4 5 14 23 32 41 50 59 68 77 86 95 104 113 122 131 140
Hrs 201816141210864200000002468
CAUTION
TO PREVENT ELECTRICAL SHOCK, CONNECT THE UNIT TO A PROPERLY GROUNDED
POWER OUTLET. DO NOT USE A THREE TO TWO PRONG ADAPTER. THIS DEFEATS SAFETY
GROUNDING.
CAUTION
DO NOT WEAR THE ESD WRIST STRAP WHEN YOU WORK ON LIVE CIRCUITS AND MORE
THAN 30 V PEAK IS PRESENT.