8-8-12-3 Verify TCP/IP Settings - Software Version v3.x
1.) From the top of the connectivity tab, select the Tcpip tab.
2.) Verify that all settings on the TCPIP tab matches those recorded in Table 8-11 "Record settings from
Tcpip screen (v3.x)" on page 8-44.
3.) Select Save settings.
4.) Select Ok to continue.
8-8-12-4 DC Offset Calibration
1.) Disconnect all probes.
2.) From the upper section of the window, select Test.
3.) Then select Go to System Test.
4.) From the Module selection block, select DC Offs. Cal.
5.) Reboot the System when the DC Offset Calibration has been completed.
8-8-12-5 Verify System Software Version
1.) Press CONFIG
(F2) and log on as adm, see 4-2-4 "Log On to the System as ‘ADM’" on page 4-12.
2.) Select about tab.
3.) Verify that the SW versions are the same as what were recorded in Table 8-13 "Record Software
and Hardware versions (v3.x)" on page 8-46.
8-8-13 Verification - Functional Checks
Please perform the tests specified in Section 8-20 "Verification - Functional Checks" on page 8-105.