Commissioning
5-3
L
EDSVS9332P-C EN 3.0
The following table briefly shows how to commission a position control according to the example
depicted in Fig. 5-1. A more detailed description of how to commission position controls can be
obtained from the following chapters.
Section Action Detailed
description
Switch on
controller
1. Assign terminal X5/28 (controller enable) to LOW signal.
2. Assign terminals X5/E1 a nd X5/E2 to HIG H signal (+13...+30V).
3. Assign terminals X5/E3 to X5/E5 to LOW signal.
4. Switch on mains:
The controller is ready for operation after approx. 1s
(2 s for drives with sine-cosine encoder with serial interface).
E 5-5
Switch on PC Start GDC on the PC
Set the communication parameters for the online mode in the dialog box ”Momentary drive”.
Confirm with ”OK”.
Select a controller in the dialog box ”Assign controller description”. Confirm with ”OK”.
E 5-6
Generate
1. Adapt controller to t he mains E 5-7
parameter set
2. Adapt controller to the motor E 5-8
3. Enter machine parameters E 5- 9
Manual control
1. Enter parameters for manual positioning or use default setting E 5-10
2. Enable controller E 5-11
3. Function test with manual control E 5- 12
Enter parameters
for traversing
profile
1. Enter positioning data in the ”Programming” dialog box.
2. Connect the X5 terminals in the ”Terminal monitor 93XX (digital)” menu
When the digital terminals X5 are supplied with internal voltage;
Assign output X5/A1 with ”FIXED1”. Approx. 24V are output to the terminal X5/A1.
TIP!
For this a pplication case one o f the predefined configurations in C0005 can be used.
C0005 = XXX1X (e. g. 20010 = absolute positioning with control via terminals) automatically assigns the
output X5/A1 with FIXED1
E 5-14
Control drive 1. Check whether the controller is ready for operation:
When the green LED is f lashing: Controller is ready for operation, go on with step 2.
When the green LED is off and the red LED is flashing: A fault has occurred. Remove the fault
before proceeding with the commissioning.
2. Enable controller
Green L ED is illuminated when a HIGH signal (+13...+30V) is assigned and no other source of the
controller inhibit is active.
3. For operation with a fieldbus module, additional settings are necessary (see Operating Instructions of
the fieldbus module).
The motor now rotates with the provided setpoint and the selected direction of rotation.