Loading...
Commissioning
5-1
L
EDSVS9332P-C EN 3.0
Part C
5 Commissioning
5.1 Before switching on
Prior to initial switch-on of the controller, check the wiring for completeness, short-circuit, and earth
fault:
Power connection:
Supply via terminals L1, L2 and L3 (direct mains connection) or alternatively via terminals
+UG, -UG (DC bus connection, network of drives).
Motor connection:
In-phase connection to the motor (direction of rotation).
Feedback system (resolver, incremental encoder, ).
Control terminals:
Controller enable: terminal X5/28 (reference potential: X5/39).
Cover of the power terminals:
Put on cover(s) and fix.
Keep to the switch-on sequence!
All commissioning steps described in this chapter refer to the default setting.
5.2 Initial switch-on
Tip!
UseaPCwiththeLenzeprogramGlobal Drive Control (GDC) under Windows for
commissioning. The convenient menu includes the codes for the most important settings.
A fieldbus module type 2102 RS232, RS485, fibre optics (Lecom A/B) is required to run the
GDC.
GDC and fieldbus module are not included in the scope of supply of the controller.